A new railway line of 142 kms among Hejjala and Chamarajanagar in Karnataka has been ready for all around 312 months or 26 decades to be laid. This is 1 of 647 assignments struggling with time overrun as on May well 1, according to a report ready by the Infrastructure and Job Management Division (IPMD) less than the Figures Ministry.
New line amongst Hejjala and Chamarajanagar is section of Bengaluru-Satyamangalam railway jobs. The project was permitted in 1996-97.
Even so, in accordance to facts put on the web-site by South Western Railway, the Tamil Nadu governing administration as properly as the Central Empowered Committee (CEC) did not given authorization to have out study in the Satyamangalam forest location.
For the duration of the calendar year 2013-14, it was made a decision that the task shall be taken up concerning Kengeri-Chamarajanagar exactly where there is no forest land included. The line was to choose-off from Kengeri but all through the study, it was observed that forest land was associated and that’s why to prevent it, the take-off station was shifted to Hejjala.
Having said that, there are even now some difficulties linked to land acquisition which is why the Railway resolved to retain this venture in abeyance. In the meantime, in November previous year, the Karnataka government wrote to the Railway “to revive the challenge saved less than abeyance by duly revising the estimate”.

Checking process
There is no update considering that then, but this challenge is one of the 211 assignments of Railway and overall, 1,559 initiatives becoming monitored by IPMD. The IPMD is mandated with checking of Central Sector Assignments costing much more than ₹150 crore in 16 sectors. It is finished by way of the system of Online Computerised Monitoring Process (OCMS).
The physical overall performance are calculated in phrases of milestones and percentage physical development from the concentrate on dates and quantities whereas the economical effectiveness is measured on a yearly basis with respect to the hyperlink expenditure on every project.
IPMD delivers out the adhering to reports and forwards the very same to the Primary Minister’s Office, the Cabinet Secretariat, the Ministry of Finance, the Scheduling Commission and the involved administrative Ministries.
Project fees
According to latest report by IPMD, predicted charge of tasks below review has long gone up to around ₹26.72-lakh crore in April as versus the original charge of more than ₹21.73-lakh crore which is about 23 per cent.
Price tag overrun with respect to original price was as minimal as 11 per cent in March 2017 and above 19 for every cent in March 2014. Similarly, time overrun has transformed from 29.44 per cent in March, 2014 to 41.5 for every cent in April, 2022.
Causes for time overruns
The report has stated a variety of reasons for time overruns as reported by a variety of undertaking utilizing businesses. These consist of delay in land acquisition, delay in obtaining forest/setting clearances, deficiency of infrastructure aid & linkages, delay in tie-up of undertaking financing, regulation & buy issues, Condition wise lockdown owing to Covid-19, beside other individuals.
It also highlighted causes of cost escalation which involve less than-estimation of authentic expense, changes in premiums of foreign exchange and statutory obligations, spiralling land acquisition fees and general price increase/inflation, beside others.
Now, the report has prepared a list of 46 jobs for focussed awareness. These have price tag overrun of 50 for each cent & extra, and time overrun of 50 months and additional. These lead practically 39 for every cent of the total price tag overrun and 20 for every cent of the whole time overrun.
“These jobs are expected to be taken up for distinctive monitoring by the respective administrative ministries,” the report claimed.
Revealed on
June 05, 2022